KLG’s Brendan Beasley and Jonathan Klavens teamed up with Mark Vitello at accounting firm BerryDunn to put together the following questions and answers relating to qualification for the 30% Investment Tax Credit (ITC) under Section 48 of the Internal Revenue Code using the safe harbor outlined by the IRS in Notice 2018-59. A version of this Q&A was previously posted on the BerryDunn website in the hope that it would be helpful to solar energy project developers and others as they navigate the last few weeks of 2019. We expect the same questions and answers will continue to be relevant prior to the year-end step-downs in the ITC over the next several years. For a short primer on the ITC safe harbor, please see Berry Dunn’s prior post on that topic .
Q: My project is not ready for construction due to a pending decision on a land use permit. How can I minimize capital expenditure while still qualifying the project for the 5% safe harbor?
A: There are a couple approaches you as a taxpayer can take. First, if this project is among several in your portfolio, you can pay or incur expenses prior to December 31, 2019 for enough safe harbor equipment under a single binding contract to qualify each project in your portfolio and retain flexibility to allocate that equipment. Applying the master contract approach (per Section 7.03(2) of IRS Notice 2018-59), you would then transfer equipment, even after December 31, 2019, to affiliate special purpose entities under a second binding contract. Second, you can enter into a binding contract that is subject to a condition, applying section (ii)(B) of the “binding contract” definition at 26 CFR Section 1.168(k)-1(b)(4). In this case, the condition would be the project receiving the land use permits and clearing any related appeals period. Under this approach you would still need to pay or incur―or have your EPC contractor pay or incur under the look-through rule―at least 5% of the project’s depreciable cost basis by December 31, 2019. A limitation on this approach is that, if the condition is not likely to be satisfied within three-and-a-half months of the date of your binding contract, either you or your EPC contractor (applying the look-through rule) must take delivery of the equipment while the condition―and presumably the viability of the project―is still open and uncertain.
Q: Can I finance a purchase of safe harbor equipment for my project?
A: Yes; however, you can’t use vendor financing.
Q: I have a project that will be ready to construct in Q2 2020. The project company will execute a binding EPC agreement by December 31, 2019 that includes a procurement component. It will make an initial milestone payment of 7% upon execution. Does my project qualify for the 5% safe harbor?
A: Maybe. There is not enough information here to confirm. As taxpayer you must pay or incur expenses amounting to at least 5% of the total cost of the energy property prior to December 31, 2019, and must take delivery within three-and-a-half months from the date of payment under your binding contract. So the critical question here is what your EPC contractor is doing with that 7% payment. Here are some possible outcomes:
- The EPC contractor purchases inverters on December 31, 2019 pursuant to a binding contract with a vendor. Applying the look-through rule, the safe harbor is satisfied.
- The EPC contractor self-constructs a specialized racking system in January 2020, per your EPC agreement, and delivers it to you within three-and-a-half months of the binding contract. The safe harbor is satisfied.
- The EPC contractor prepares 10% construction drawings and applies for a building permit, each at nominal cost, and holds your 7% payment while waiting for module prices to come down. The safe harbor is not satisfied.
- The EPC contractor allocates its previously purchased inverters to your project, per your EPC agreement, holding them in its warehouse until May 2020 before delivering them to your site. The safe harbor is likely satisfied. Applying the look-through rule, the EPC contractor’s purchase of the inverters pursuant to a binding contract in 2019 (even if prior to the EPC agreement) will qualify the inverters for safe harbor purposes. The EPC contractor must take steps to identify and segregate the particular inverters within its warehouse.
Q: Can I sell safe-harbored equipment?
A: The buyer of your equipment (unless it is an affiliate) may not utilize the safe harbor unless you are selling the equipment together with the solar project. If, for example, your sale also includes a site lease and a PPA, the purchaser would receive the benefit of the safe harbor. In certain circumstances, you may also be able to become an affiliate of a project LLC by acquiring a membership interest of at least 20% and make an in-kind contribution of the safe-harbored equipment to the project LLC.
Q: Can I satisfy the physical work test by building roads within my site?
A: Yes; however, the roads must be integral to the energy property. An access road would likely not be interpreted as integral to the property. However, roads used for purposes of operations and maintenance activity―within the area of the facility itself―are considered integral to the energy property.
Q: What constitutes work of a physical nature?
A: This is really open to the facts and circumstances interpretation. The IRS notice instructions referenced previously indicate some specific activities that do not qualify, but there is no quantification of how much of a qualifying activity must be done in order to satisfy the safe harbor requirement. Preliminary planning and site work do not count. But starting construction would, so you could satisfy the requirement with excavation for a foundation, drilling for moorings, pouring concrete, etc. The best bet would be to actually put up a section of panels.
Q: What is the continuing work requirement?
A: There is an additional safe harbor that provides that, if your project is placed in service within four years of the end of the calendar year in which you started it, you will have automatically met the continuous work requirement. If your project goes beyond that you will need to show facts and circumstances showing you were taking steps to continue working towards completing the project. For example, if the delay was due to a delay in getting interconnected, be prepared to show documentation that you were continuously working towards resolving that issue.
Unless there are changes to the current tax law, these same provisions will be in effect for each step of the phase-out through the end of 2023.
FURTHER INFORMATION
For further information about these matters, please contact Brendan Beasley at bbeasley@klavenslawgroup.com or 617-502-6288 and Jonathan Klavens at jklavens@klavenslawgroup.com or 617-502-6281.
DISCLAIMER
This document, which may be considered advertising under the ethical rules of certain jurisdictions, is provided with the understanding that it does not constitute the rendering of legal advice or other professional advice by Klavens Law Group, P.C. or its attorneys. Please seek the services of a competent professional if you need legal or other professional assistance.
© 2019 Klavens Law Group, P.C. All rights reserved.